Turnkey Solution for Sika Christchurch

Tuesday, February 25th, 2025

Job number #16014

Location: Christchurch, NZ

Time: October 2024 – March 2025

Taurus was engaged by Sika Christchurch to deliver a comprehensive turnkey solution, covering the design, fabrication, and installation of multiple components. At the core of this project was the mixing tank, designed and integrated with supporting structures and process systems to ensure optimal functionality.

Our scope of work included: 

  • Designing: To meet all legislative requirements for health and safety, safe operation, and design best practices/standards, including mechanical, structural, electrical, automation and process pipe flow systems. 
  • Fabricating and Installing: a mezzanine platform with handrails, product platforms with load cells, and a crane hoist and crane structure. 
  • Manufacturing and Integrating: the mixing tank with process pipework, pumps, and valves, including electrical systems and full automation—thanks to Millennium Electrical. 
  • Installing key operational elements, including a scrubber unit, pallet swing gate, and water tanks. 

The project is currently underway, with work progressing towards a fully integrated system that meets Sika Christchurch’s operational needs. 

 

 

Posted in

Fabrication of Wet Scrubber and Structural Frame for NZ Steel

Tuesday, February 18th, 2025

New Zealand Steel, the country’s leading producer of flat rolled steel products, operates from the Glenbrook Steel Mill, 40 kilometres south of Auckland. Serving industries such as construction, manufacturing, and agriculture, the company is dedicated to enhancing sustainability and efficiency in steel production.

As part of the Melters Extraction upgrade, Taurus played a pivotal role in fabricating key components for the project. This upgrade was designed by Vortex to improve the performance of the Melter feed bin de-dust system, which removes hot dust and fumes generated during the batch feeding of hot materials into the 24 charging bins (12 per Melter) associated with the two Melter units.

Taurus’ Contribution

Taurus’ scope of work in this project included the fabrication of the six-metre-high wet scrubber and the structural frame. Key contributions included:

  • Fabrication of the Wet Scrubber: Taurus constructed the wet scrubber using high-grade 3Cr12 stainless steel, selected for its ability to withstand the challenging environment of high temperatures and abrasive materials. The scrubber was designed to effectively remove remaining dust load and gaseous emissions before they are safely released into the atmosphere.
  • Structural Frame: The structural frame was fabricated with carbon steel to provide robust support for the system. Taurus ensured precise engineering and manufacturing to handle the load requirements and ensure durability in the demanding operational environment.

 

Taurus’ expertise in fabrication ensured the successful completion and delivery of the wet scrubber and structural frame. A complete trial build of the system was performed to confirm that all components were ready for seamless installation.

The system was installed on schedule and is operating as intended. With the upgraded system in place, New Zealand Steel has noted an improvement in the work environment, contributing to their goals for sustainability and efficiency under Project Electron.

Posted in

Pressure Vessel for the chemical industry

Wednesday, May 10th, 2023

Location: Melbourne, Australia

Year: March 2023

 

In early 2023, Taurus Engineering partnered with a company in Queensland, Australia, to deliver a pressure vessel for air purification in the chemical industry in Melbourne.

 

Build for demanding applications

The pressure vessel was built to the main specification of AS1210 Class 3 Pressure Vessel, with additional examination and pressure testing required to be done to Spec (4037-1999_R2016). All welding was done to ASME IX specs.

Constructed using grade 304 stainless steel with thicknesses between 5mm and 20mm, the vessel was made of plate, pipe, fasteners, rod, and machined flanges. These materials were chosen for their strength, malleability, and resistance to corrosive environments and applications.

 

Designed for corrosion challenges

The vessel was designed for a specific application in the chemical industry. However, due to its use, there were potential corrosive challenges that needed to be considered during the construction process.

Welding the pressure vessel presented multiple challenges, including Die Pen testing and 100% visual examination, as the vessel needed to meet the hazardous Class 3 specifications. Quality assurance checks needed to be thorough, and all material certificates were checked upon arrival. Multiple parties were involved in the welding process to ensure that no preparation was missed and that all quality assurance documents showed compliance with the AS1210 Class 3 specs.

The vessel had a capacity of 3.6 m3 and a maximum operating pressure of 0.58 bar. Its technical details made it unique and of particular interest to the chemical industry. The successful delivery of this pressure vessel demonstrated our expertise in meeting the specific needs of clients in the chemical industry and our commitment to meeting the highest quality standards.

Posted in