Turnkey Solution for Sika Christchurch

Tuesday, February 25th, 2025

Job number #16014

Location: Christchurch, NZ

Time: October 2024 – March 2025

Taurus was engaged by Sika Christchurch to deliver a comprehensive turnkey solution, covering the design, fabrication, and installation of multiple components. At the core of this project was the mixing tank, designed and integrated with supporting structures and process systems to ensure optimal functionality.

Our scope of work included: 

  • Designing: To meet all legislative requirements for health and safety, safe operation, and design best practices/standards, including mechanical, structural, electrical, automation and process pipe flow systems. 
  • Fabricating and Installing: a mezzanine platform with handrails, product platforms with load cells, and a crane hoist and crane structure. 
  • Manufacturing and Integrating: the mixing tank with process pipework, pumps, and valves, including electrical systems and full automation—thanks to Millennium Electrical. 
  • Installing key operational elements, including a scrubber unit, pallet swing gate, and water tanks. 

The project is currently underway, with work progressing towards a fully integrated system that meets Sika Christchurch’s operational needs. 

 

 

Posted in

Lyttelton to Woolston pipeline

Thursday, January 26th, 2023

Location: Lyttelton, NZ

Schedule: 2020-2021

 

In 2020, Taurus Engineering executed the Lyttleton to Woolston pipeline upgrade, which required 1.2 km of 150mm HD steel buried pipeline and valves. Taurus worked with various partners to complete the project in 2021. 

 Among the challenges that had to be overcome were: traffic management; public safety; and the protection of council assets that were buried under ground. 

 

Posted in