Walkway and Support Structures for Project Pure

Monday, April 7th, 2025

Job#16069  

Location: Wanaka, NZ

Time: Oct 2024 – Mar 2025

 

As part of an infrastructure upgrade at the Wanaka Wastewater Treatment Plant, a comprehensive fabrication and supply project was initiated to enhance the facility’s operational efficiency and safety.  

The existing water waste treatment plant was established in 1988. The plant was upgraded in 2000 and has now reached capacity and is due for an upgrade. In 2025, Taurus was selected to supply and fabricate key components for the plant’s new walkway and support structures. The scope of work included the fabrication of 6 walkway modules, 7 walkway pipe supports, handrails for the modules, and a stairway as well as the supply of FRP mini mesh grating and clip sets. Despite the project’s complex requirements and the need for precise fabrication to meet engineering specifications, Taurus successfully completed all fabrication work, with items hot dip galvanised for durability and corrosion resistance. The finished components were delivered to the Wanaka Wastewater Treatment Plant according to the agreed timeline.  

Since the initial fabrication and supply of key components for the walkway and support structures, additional work ongoing, includes the outer manifolds, cross pipes, and a manifold central to improve the flow and control of the wastewater treatment process… These modifications have optimized the plant’s operational efficiency and accessibility for maintenance tasks. These upgrades, along with the original scope of work, have collectively contributed to the overall success of the project, reinforcing Taurus’s commitment to precision, durability, and seamless integration of complex systems. 

 

Posted in

Turnkey Solution for Sika Christchurch

Tuesday, February 25th, 2025

Job number #16014

Location: Christchurch, NZ

Time: October 2024 – March 2025

Taurus was engaged by Sika Christchurch to deliver a comprehensive turnkey solution, covering the design, fabrication, and installation of multiple components. At the core of this project was the mixing tank, designed and integrated with supporting structures and process systems to ensure optimal functionality.

Our scope of work included: 

  • Designing: To meet all legislative requirements for health and safety, safe operation, and design best practices/standards, including mechanical, structural, electrical, automation and process pipe flow systems. 
  • Fabricating and Installing: a mezzanine platform with handrails, product platforms with load cells, and a crane hoist and crane structure. 
  • Manufacturing and Integrating: the mixing tank with process pipework, pumps, and valves, including electrical systems and full automation—thanks to Millennium Electrical. 
  • Installing key operational elements, including a scrubber unit, pallet swing gate, and water tanks. 

The project is currently underway, with work progressing towards a fully integrated system that meets Sika Christchurch’s operational needs. 

 

 

Posted in

Taranaki Street Pumpstation

Friday, January 19th, 2024
Location: Wellington, New Zealand
Time: July 2022 – March 2024
Partner: Brian Perry Civil

Job number #15202 

 

Back Ground

This project, situated in central Wellington, was undertaken to address urgent challenges within the city’s wastewater system. Its main goals included seamlessly integrating a new pump station into the existing wastewater network, optimizing flow redirection, and preparing for a future connection to the Taranaki Street Rising Main. The driving force behind this initiative was to overcome the limitations of the current wastewater system, expand its capacity, accommodate future growth, and enhance the robustness of vital wastewater infrastructure.

The intricacies of the project were notable, with the pump station boasting a 10.88m external diameter and 8.66m internal diameter, situated approximately 8.5m below ground level.

 

Scope of Work

Our scope of work was comprehensive and included:

  • Installation of inlet pipes into the wet well.
  • Dry well-side, encompassing the installation of all suction and discharge pipe work.
  • Creation of a mezzanine platform.
  • Implementation of internal and external HVAC systems for heating, ventilation, and control.
  • Installation of a lift beam.

Challenges and Solutions

Several challenges emerged during the project, and innovative solutions were required to overcome them.

  1. First, adverse weather conditions presented a hurdle, particularly on rainy days when water inundation into the pump station was a concern.
  2. Additionally, heavy rainwater filled the HVAC system, causing damage to both inlet and outlet fans. Manoeuvring within a tight urban space, and the need for early morning deliveries to minimize disruption in the city centre, presented logistical challenges.
  3. Furthermore, managing a project in Wellington while our staff was based in Christchurch required streamlined communication, and efficient issue resolution, as well as timely deliveries from Christchurch to Wellington.

 

The project achieved its objectives successfully and within the stipulated timeframe and budget. Client satisfaction was paramount, with our work meeting high standards and quality expectations. Effective communication and collaboration with BPC played a pivotal role in swiftly resolving potential issues. This project not only addressed critical wastewater network challenges but also showcased our ability to execute complex projects in confined urban settings with efficiency and professionalism.

By maintaining a pragmatic and straightforward approach throughout the project, we delivered results that met the client’s needs and upheld our commitment to excellence in engineering solutions.

 

*Photo credit: Brian Perry Civil and Wellington Water.

Posted in

Sydenham Pump Station Suction Tank Project

Tuesday, October 24th, 2023
Location: Christchurch, New Zealand 
Schedule: July 2023 – September 2023
Partner: Seipp Construction

Job number #15348

 

Project Background

As part of the Council’s infrastructure improvements, the old Sydenham suction tank was replaced. Taurus was tasked with providing the pipework connecting the new tank to four existing well heads and a pump station. Additional structural installations such as a surrounding stairway and pipe supports were also part of the project.

Scope of Work

  • Overflow & Stormwater
  • DI/SS Pipework
  • Structural Work (external tank stairs, step-over platform)

Challenges and Solutions

A sudden change in material and specifications was effectively managed by Taurus, who chose to use stainless steel pipes, allowing for a quick turnaround and minimal impact on the project timeline.

Taurus introduced a socketed pipe system for the underground sections, a first for all involved. Close communication with the supplier and the Council led to an alternative locking mechanism, negating the need for thrust blocks.

Some existing infrastructure was not aligned either parallel or perpendicular, which is fairly standard. This was effectively handled through on-site pipe fabrication, facilitated by our Hamilton crane, which enabled the easy manoeuvring of larger pipe sections.

Designing and installing the stairway was challenging due to its complex geometry and location. Through effective communication between our project office and the fabrication floor, the stairway was successfully installed.

Outcome

All components were fabricated and installed successfully. The experience has enriched Taurus’ project office and site team, equipping us with valuable skills for future projects.

Posted in

Pressure Vessel for the Chemical Industry

Wednesday, May 10th, 2023

Location: Melbourne, Australia

Year: March 2023

Job number #101967

In early 2023, Taurus Engineering partnered with a company in Queensland, Australia, to deliver a pressure vessel for air purification in the chemical industry in Melbourne.

 

Build for demanding applications

The pressure vessel was built to the main specification of AS1210 Class 3 Pressure Vessel, with additional examination and pressure testing required to be done to Spec (4037-1999_R2016). All welding was done to ASME IX specs.

Constructed using grade 304 stainless steel with thicknesses between 5mm and 20mm, the vessel was made of plate, pipe, fasteners, rod, and machined flanges. These materials were chosen for their strength, malleability, and resistance to corrosive environments and applications.

 

Designed for corrosion challenges

The vessel was designed for a specific application in the chemical industry. However, due to its use, there were potential corrosive challenges that needed to be considered during the construction process.

Welding the pressure vessel presented multiple challenges, including Die Pen testing and 100% visual examination, as the vessel needed to meet the hazardous Class 3 specifications. Quality assurance checks needed to be thorough, and all material certificates were checked upon arrival. Multiple parties were involved in the welding process to ensure that no preparation was missed and that all quality assurance documents showed compliance with the AS1210 Class 3 specs.

The vessel had a capacity of 3.6 m3 and a maximum operating pressure of 0.58 bar. Its technical details made it unique and of particular interest to the chemical industry. The successful delivery of this pressure vessel demonstrated our expertise in meeting the specific needs of clients in the chemical industry and our commitment to meeting the highest quality standards.

Posted in

Lyttelton to Woolston pipeline

Thursday, January 26th, 2023

Location: Lyttelton, NZ

Schedule: 2020-2021

Job number #15899

In 2020, Taurus Engineering executed the Lyttleton to Woolston pipeline upgrade, which required 1.2 km of 150mm HD steel buried pipeline and valves. Taurus worked with various partners to complete the project in 2021. 

 Among the challenges that had to be overcome were: traffic management; public safety; and the protection of council assets that were buried under ground. 

 

Posted in