Constructed in 1887, the existing single-lane bridge over the Clutha River – Mata-Au on SH8, serving Dunedin, Central Otago, and Queenstown, was no longer sufficient for the heightened traffic and the demands of heavier lorries we see today. To accommodate the current and projected traffic growth, including the traversal of heavier trucks, and to adhere to modern earthquake standards, a contemporary two-lane bridge began in the works. The historic bridge has retained its place even after the inauguration of the new one, providing a connection to the popular Clutha Gold walking and cycling trail.
Taurus, contributing through HEB Construction, has supplied Shear Keys, Service Duct Hangers, Pedestrian Balustrade, and Barriers Cover Plates for the project.
The new bridge was ceremoniously unveiled on 30th July 2023. A large contingent of local residents participated in the event, crossing the new bridge collectively in celebration of its inauguration.
Taurus is deeply honoured to have had the opportunity to make such a significant contribution to the community.
*Photo credit: NZ Transport Agency & HEB Construction
Reference links:
https://www.nzta.govt.nz/projects/new-beaumont-bridge
https://www.youtube.com/watch?v=v00q8S_vNIM
Posted in
Location: Ashburton, New Zealand
Schedule: 2021 -2022
Taurus provided steel fabrication for the new Surrey Hills Bridge in Ashburton and ensured certification. The bridge is on the Rangitata Division Race (RDR) on Canterbury’s Inland Scenic Route. It was completed in early 2022.
Taurus supplied and installed structural steel works as part of the re-strengthening project for Christchurch Art Centre’s F & B blocks throughout 2019-2022. (F block is completed and B block is still on going.) The Observatory Hotel is also complete.
Taurus supplied and installed stainless metal work for the Ravenscar House Museum in Christchurch, New Zealand, in 2020-2021.
This house in Scarborough was heavily damaged by the Christchurch earthquake in February 2011 and it has been restored.